Britain cut the queue for the electricity grid. Why are so many projects getting later dates?

Two Coordinated Solutions colleagues talking beneath the company sign.

Photo credit: Helen Rowan.

One energy developer told the Financial Times that the date they'd been given to connect a project to Britain's electricity network had moved back by two years. This was after the queue had been cleared of projects unlikely to get built, to make way for those that were ready. You can understand the developer's frustration. But before asking a project team to find a way to win back those two years, we'd want to know what made anyone believe they had them in the first place. Financial Times, 19 November

A wind farm needs a way to get its power to the people who will use it. Having permission to build turbines is one thing. Having the electricity network ready to take their output is another. For years, projects could secure a place in the queue largely on the strength of when they applied. Britain changed the system so that speculative proposals would stop holding up projects with a better prospect of going ahead. Last week Ofgem, the energy regulator, said the queue was in better shape but most of the projects left in it were looking at later dates. It has opened an inquiry into why so many of the projects given priority have seen their offers pushed back. Background to the reform · Ofgem's inquiry

Two months earlier, an MP had put much the same question rather more bluntly. In a parliamentary committee hearing, Mike Reader asked energy minister Michael Shanks who was to blame for the delays. Shanks described developers who had been offered a connection just a year away when the construction needed to connect them hadn't even started. In his judgement, many of the dates people were relying on had never been achievable. That's his account of the old system. We don't know whether it explains the two years in the developer's account. That gap is precisely what makes this a project leadership story. Parliamentary evidence, question 309

Consider what each account asks you to do. If a network company could have made the original date and lost time waiting for a decision, it's worth finding the person who can make that decision and working out how much time they can still save. If the date was offered before anybody had allowed enough time for construction, telling the engineers to recover the delay gives them a fairly peculiar job. They're being asked to win back time they never had. Worse, a sponsor may approve more spending in the quite reasonable belief that the original promise can still be bought back.

The developer gave the FT a third reason to look more closely. In their experience, uncertainty during the review itself had held up decisions. An old promise can be unrealistic and the process of correcting it can cost somebody real time. Accepting the minister's explanation for one part shouldn't let anybody off the hook for the other. Ofgem intends to examine differences between network companies and make the construction assumptions behind offers clearer. Those details matter rather more to the person waiting to connect than another assurance about their place in the queue.

What to ask when a project deadline moves

If this were a project we were leading, we'd put the two dates to one side for the first few minutes and ask the people doing the job to describe what is left to do. Which activity determines the earliest possible finish? What needs to happen before it can start? Who has confirmed when that will be? Only then would we bring the original offer back and look for the first place where its assumptions differed from what we now know.

There's a reason for doing it in that order. Once a date has been promised to a customer, it becomes the starting point for almost every conversation that follows. Ask how far behind you are and people set about calculating the distance from it. Ask what it would take to finish and they can start with the job itself. Psychologists call that pull towards an initial estimate anchoring. An independent estimate gives the sponsor a useful second opinion while there's still time to act on it. Research on anchoring and judgement

We'd keep the old offer in the board papers. The customer may already have made commitments on the strength of it, and replacing it with a fresh date would quietly remove the very promise somebody ought to account for. Alongside it we'd put the earliest date the delivery team can now defend, what changed, and any decision the sponsor could take to improve it. If a decision was late, say whose decision is needed now. If the original estimate omitted necessary construction, say who will explain that to the customer and what evidence they'll bring. That distinction is part of the diagnostic work we do in The Delivery Reset.

Moving somebody back two years on paper is bad news they deserve to have explained. It still leaves a sponsor with a choice about what to do on Monday morning. Before buying a recovery plan, ask the person proposing it which part of the job it will bring forward, by how much, and who has checked that the time is there to save.